INFOKU, BLORA –There was a road project last year that was delayed or not completed until the end of December 2022.
Contractors were subject to fines, a total of around IDR 700 million was collected. DPRD Blora evaluates and asks for accelerated planning, so that work is not delayed.
Secretary of the Public Works and Spatial Planning Service (PUPR) Blora Nizamuddin Al Hudda said contractors whose work was delayed were subject to fines.
As a result, around Rp. 700 million was collected and put into the regional treasury (kasda) managed by the regional revenue, finance and asset management agency (BPPKAD).
This year, the district government is trying to speed up the planning and process of infrastructure project work. Some have progressed and completed the auction.
Also read: Rp. 400 million to replace 48 PJU lamps
"Including the road from DAK, the auction has been completed, it will be implemented immediately," he explained.
DPRD Commission C member Blora Darwanto said the regency government needed to take steps to prevent project completion from not being on target.
He suggested, this year's development planning accelerated.
Also read: Road Projects Budgeted Rp. 90 Billion in 82 Strategic Section Points
"Development planning should be completed at the end of February, so that the bidding process will take place in March," he said.
According to Darwanto, if the process goes smoothly, it is estimated that the project will be carried out next April.
The processing time is usually three to four months. So that before December all projects can be completed. Also dry season work, so the quality of work is good.
"Hopefully by September all development work will be completed. You don't have to wait for the end of the year," he said. ( Endah / IST )