Entering the Final Stage, Only 26 Road Projects Com


INFOKU, BLORA –  A number of contractors received warning letters (SP) along with the progress of the work which was considered to be slow.

This is because the road project is entering its final stage.

Of the 90 points of road projects in the regions, only 26 partners have handed over the results of the work.

"A week ago 26 packages submitted PHO (handover)," said Head of Highways of the Public Works and Spatial Planning (DPUPR) Blora Nidzamudin Al Hudda yesterday (7/11).

He said, gradually several road projects have been completed. This year there are 90 road construction points and 26 road sections have been handed over.

The road infrastructure project is estimated to be completed in December.

Also read:  How to get a free set top box from the government

The road project with a length of 109,013.47 meters has been budgeted at around Rp 307 billion.

Previously, he said, several partners had received warning letters because the work was deemed slow.

This was revealed in the show cause meeting (SCM) as proof of delays in construction work.

The head of the PUPR Service, Samgaumata Karnajaya, said that even though the contractors had received SP-1 and SCM-II, they were still able to complete them.

"Still able. I'm sure the work will still be done," he explained.

Also read:  Ganjar Asks Regional Heads Not to be Careless  regarding Inflation

So far, no contract has been terminated. He hopes the partners can finish the job to the end. Even if a contract is terminated, it will be troublesome for the progress of the work.

"It is not certain that the replacement or the appointed one can complete the work and want to do it," he said. (EndahIST ) 